Data Center Conditional Use Permit on South Fort Hood Street
Killeen
Summary
A developer wants to build a 30 million dollar research data center next to an electric substation on South Fort Hood Street. Commissioners reviewed noise, lighting, and utility requirements to ensure the project fits the area without disturbing neighbors.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Apr 27, 2026.
Impact analysis
Estimated capital investment of approximately 30 million dollars by the private property owner.
The property owner and local technological infrastructure development.
Nearby property owners could be impacted by noise or light trespass if mitigation conditions are not strictly enforced.
Mentions & discussions (1)
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Killeen
What the council decided, in plain English — one email a week.